Assign a Fixed Cost to a Task

When you know exactly how much the materials will cost for a task, or you’re not assigning resources to the task, enter a fixed cost. A fixed cost might be the cost of supplies for which you’ve already negotiated a purchase price. It could also be a bid you accepted from an outside contractor or the flat rate you always pay for a job.

To assign a fixed cost to a task

  1. On the View Bar, click Gantt Chart .
  2. On the View menu, point to Table, and then click Cost.
  3. In the Fixed Cost field, select the task, and then type the cost.
  4. Click or press ENTER.