Assign a Group of Resources to a Working Times Calendar
After you create a base calendar, you need to assign the calendar to each resource that will be using it.
To assign resources to a working times calendar
- On the View Bar, click Resource Sheet
.
- In the Base Calendar field of each resource you want to assign to a calendar, select the same base
calendar.