Assign a Group of Resources to a Working Times Calendar

After you create a base calendar, you need to assign the calendar to each resource that will be using it.

To assign resources to a working times calendar

  1. On the View Bar, click Resource Sheet .
  2. In the Base Calendar field of each resource you want to assign to a calendar, select the same base calendar.