Change or Remove a Task Link
If the link between tasks doesn’t accurately reflect the dependency between those tasks, you can easily
change the type of link that connects them. If you later decide that you don’t want a link between particular
tasks, you can remove that link.
To change a task link
- On the View Bar, click Gantt Chart
.
- Double-click the link line of the tasks you want to change.
- In the Type box, click the task link you want.
To remove a task link
- On the View Bar, click Gantt Chart
.
- In the Task Name field, select the tasks you want to unlink.
- Click Unlink Tasks
.
The task will be rescheduled based on any other dependencies.