Update Information in a Resource Pool

Whenever you change resource information in a project that shares a resource pool, you must update the pool so that the latest information is available to all the other projects that share the pool.

To update information in a resource pool

  1. Open the project that shares the resource pool.
  2. On the Tools menu, point to Resources, and then click Update Resource Pool.