Change the Report Period, Display Overtime Work, and Modify Other Options of Your Task List in the
TeamInbox
By default, the Task List shows the days of the week that compose the report period. For example, if the report
period is from Monday 12/30 to Sunday 1/5, you’ll see a column for each day of the week in that period.
However, you can change the report period or the time units displayed in the Task List.
The time units that are available include:
- Total for the entire period, which displays a separate field for the total amount of work that has been
performed on the task.
- Day, which is the default setting and displays a separate field for each day in the report period.
- Week, which displays a separate field for each week in the report period. This option is helpful when the
tasks continue for several weeks.
When you change the timescale, all the work values currently saved in the Task List will be erased. You can
also choose to display overtime work and change the day on which the week starts.
To change the options of your Task List
- Open your TeamInbox.
- Click Task List, and then click Options.
- In the Period From and to boxes, enter the new dates for the report period.
These two dates are included as part of the report period.
- In the Broken down by box, click the timescale by which the Task List will display tasks.
- To change the day on which the week starts, click the day you want in the Week starts on box.
- To display overtime work in the Task List, select the Display Overtime Work check box.
- To save your changes, click Set new period options.