Despite your best efforts and all the advice in this book, it might still turn out that your baseline doesn’t reflect project reality accurately enough to remain an effective tracking tool. Perhaps some of your task estimates were knocked off target because of unpredictable factors. Or, upper management decided to move up the project finish date, which means you may need to shrink task durations. At such times, you’ll need to change the baseline information for tasks.
To change baseline information for one or more tasks
or any other task
view.