Format a Category of Tasks or Resources
Sometimes you may want to format one particular category of tasks or resources so that it stands out from the
rest. For example, to keep a sharp eye on critical tasks you may decide to make all critical task names italic.
You can format categories of tasks and resources in all views except form views.
To apply formatting to a task or resource category
- On the View Bar, click the view you want to reformat.
To select a view that doesn’t appear on the View Bar, click More Views
, click the view you want in the Views list, and then click Apply.
- On the Format menu, click Text Styles.
- In the Item to Change box, click one task or resource category to reformat, and then select
formatting options for that category.
- Repeat step 3 to change the formatting of other categories of information.