If you don’t want to reschedule any of the tasks to which an overallocated resource is assigned, and yet you want to avoid removing the resource from any of the assigned tasks, there’s another way you can free up some time. You can assign the resource to work part-time on each of the tasks that occur during the overallocated period.
To reassign a resource to work part-time on a task
| You can leave the Resource Assignment dialog box displayed as you work. |
.
.
or press ENTER.