Because critical tasks are the ones that affect project length, the longest critical tasks have the biggest effect. When it’s important to maintain or shorten the project length, you’ll want to focus first on shortening the critical tasks with the longest duration. You can do this most easily by sorting critical tasks by duration.
To sort critical tasks by duration
.